Upstroke movable support system bridge making machine
Upstroke movable support system bridge making machine

Bridge making machine 1. Save cost 2. Convenient use 3. Simple operation 4. For erecting bridge

Work Steps of the Upstroke Movable Support System Bridge Making Machine with 32m Standard Span

Step 1:

after stretching the box girder, remove scattered formwork and side formwork equipments at top of the pierremove vertical, horizontal connection bolts in the boom, bottom formwork and lateral formwork, remove transverse joint bolts in the formworkhydro-cylinder in the auxiliary support leg stretches out to the bridge, cylinder in the rear support leg takes back and moves forward to a certain place, hanging in the airsupport cylinders in the auxiliary support leg and front support leg take back to make the whole machine fell 0.27mbottom formwork moves transversely to start and be locked temporarily, preparing for moving from one pier to next pier first time

Step 2:

start longitudinal moving mechanism of the bridge making machine to make the whole machine move forward to 10.7m, then stopcylinder in the rear support leg of the bridge making machine lifts tightly to conversion fulcrum of the main girder, cancel the lock between front support leg and top of the piercylinder in the rear support leg lifts up to 0.1m, the front support leg hangs in the air to prepare for moving forward

Step 3:

auxiliary support leg is fixed with prestressed reinforcing steel or with reserved boom hole in the bridge deckfront support leg hangs on the air to move forward to assigned location on the top of the pier to be installed, tension the upright and temporary inclined bars on top of the pier, fix the upright with built-in fittings. After being confirmed by check, take back the cylinder in the rear support leg to prepare for a second time moving forward

Step 4

start longitudinal moving mechanism of the bridge making machine to make the whole machine move forward about 22mmoves transversely to close the bottom formwork, connect connection bolts between left formwork and right formworkcylinders in the rear support leg and front support leg lift up to 0.27m to working condition, then fix theminstall the boom and adjust it, measure the formwork and adjust it, remove temporary inclined bars of the front support leg uprighttie up bottom formwork, sternum rebar and prestressed reinforcing steelfinish installing dismounting type internal formworktie up top slab rebar and prestressed reinforcing steelcast box girder concrete and maintain itmaintain the concrete to certain tension strength , have a prestressed tension work

Upstroke movable support system bridge making machine

Ads by Google


About Us | Contact Us | Help | Terms & Conditions
Hot Products: A | B | C | D | E | F | G | H | I | J | K | L | M | N | O | P | Q | R | S | T | U | V | W | X | Y | Z | 0-9
Copyright Notice @ 2008-2022 ECBAY Limited and/or its subsidiaries and licensors. All rights reserved.